Stormwater & Drainage Restoration
Project Phases Click any phase to expand
P0
Site Cleanup & Restart Preparation
0%
▾
- Week 1 — Landscape & perimeter cleanup: general debris / overgrowth removal across the project area; haul away residual material from prior work so the site is safe to re-enter.
- Week 1–2 — Take down the old / existing silt fencing left by the prior contractor; stage for disposal.
- Week 2 — Fill open trenches & holes left from the prior scope so the site is level and safe for Phase 1 mobilization.
- Week 2–3 — Remove the old pipe where previously installed and no longer needed under the current drainage design.
- Week 3 — Pre-grading & final site prep so the surveyor can lay out from a clean reference and the new work can start on Day 1 of NTP without rework.
- JNL Land Management performs the complete reset within Schedule IV (Rework & Temporary Access) — included at $29,363.69 covering flowable-fill demo & hauling, complete jobsite cleanup & restart prep, loader w/ forks for plates, and the steel plates themselves.
P1
Mobilization & Site Prep
0%
▾
- Day 1: LS Mobilization — equipment moved to the easternmost grass area past the pool equipment (per Addendum #1 Q6); MOT devices + port-o-let staged
- Day 1–2: 811 locate call — all underground utilities marked prior to any excavation
- Day 2–3: LS Layout staking by Land Precision Corporation
- Day 3–5: 300 LF NEW silt fence install by Ranger Supply — both sides between unit patios and the work area (per Addendum #1 Q7)
- Day 5–7: 13 EA Inlet / M.E.S. protection on every structure in the drainage area
- Pre-mob coordination with the HOA for resident access + Russell Landscape for irrigation shut-down (per Addendum #1 Q1)
P2
Earthwork, Palm Removal & Drainage Prep
0%
▾
- 24 EA Palm stump grinding — grind to a depth that accommodates regrading; stumps are NOT fully removed (Addendum #1 Q2)
- 6,600 SF Pre-grading of swales — final drainage profile ahead of pipe install (built on top of the Phase 0 pre-grade)
- Final staging of drainage materials delivered during the soft-NTP window
- JNL continues from Phase 0 directly into pipe-work subscope through Phase 3 (no re-mob required)
P3
Storm Drainage Installation · CRITICAL PATH
0%
▾
- 196 LF 8" PVC pipe — $37,218.44
- 162 LF 10" PVC pipe — $37,559.70
- 96 LF 12" PVC pipe — $28,086.72
- 11 EA 12" Drain basin w/ grate — $15,675
- 7 EA Single downspout assemblies · 5 EA Double downspout assemblies
- 17 EA Tees & reducers (8x6, 8x8, 10x6, sweep + 8x6 reducer)
- 2 EA Concrete M.E.S. (National Concrete)
- Flowable fill around pipe up to 6" limerock base per Addendum #1 Q5 — CLSM, 50–150 psi
- Pipe bedding + bedding around basins = #57 crushed stone, except where flowable fill is required
- Stub included in the last drainage basin for future tie-in connections
P4
Road & Concrete Restoration
0%
▾
- 11 SY Asphalt pavement trench cut (min 3' per spec)
- 11 SY Asphalt pavement replacement by Specialty Paving
- 25 LF Concrete sidewalk removal & replacement (4" thick / 3,000 psi) by National Concrete
- 4 EA Concrete curb cuts & replacement (joint to joint — adjusted per Addendum #1 Q4)
- MOT Plan active — anticipated road closure Mon–Wed of a single week (approx 1.5 weeks total) with road-closed signage
- Steel plates installed over active trenches for driveway crossings (Schedule IV) + onsite loader w/ forks for plate handling
P5
Final Grading, Sod & Closeout
0%
▾
- Final grading across all disturbed areas (6,600 SF of swale)
- 6,925 SF Sod placement — contractor's responsibility per Addendum #1 Q3 (covers all exposed soil, prevents erosion)
- Erosion-control maintenance continues until site stabilizes
- SWPPP take-down — silt fence & inlet protection removed after stabilization
- LS Certified as-built plans by Land Precision Corporation
- Final walk-through with NV5 inspector & Jose Cuarta, P.E. — punchlist resolution
- Final pay app + partial release of lien from FFAC and every sub/vendor (per NV5 Clarification #5)
···
Across Every Phase
▾
- FFAC provides for project duration: MOT devices, port-o-let w/ handwash station, erosion-control maintenance
- Full PPE every day (hardhats, hi-vis vests, safety boots)
- Designated spotters for truck movements; backup alarms on every vehicle
- End-of-day equipment staging in designated area; worksite left clean & orderly
- Russell Landscape coordinates irrigation shut-downs with 24h notice
- Weekly progress email to the HOA Board + NV5 (Fridays)
- Daily sign-in sheets, weekly Toolbox Talks, SWPPP inspections filed in Documents tab
Team & Contacts
- 9343 Blind Pass Rd, St. Pete Beach, FL 33706
- Engineer of Record — NV5, Inc.
- Jose R. Cuarta, P.E. — Project Manager, NV5
- 10500 University Center Drive, Suite 230, Tampa, FL 33612
- Office (813) 765-4655
- NV5 inspector = daily onsite contact for progress & pay-app review
- Joe Santerelli — Project Manager (Primary On-Site) · 352-263-1551
- Arthur Wilmoth — CEO / President (Secondary) · 813-853-6597
- 10701 N Nebraska Ave, Tampa, FL 33612
- Florida License CBC1267421 · Certified Building Contractor
- 5 years in construction work of this type (per Bid Submittal)
- Site inspected Sep 22, 2026 by Arthur Wilmoth
- JNL Land Management — Clearing, grubbing, grading, pipe work & complete site cleanup (John attending Board meeting with Joe & Arthur)
- Specialty Paving — Asphalt pavement replacement (Schedule II)
- National Concrete & Construction — M.E.S., sidewalk, curbing, flowable fill, catch-basin collars
- Ranger Supply — Furnish & install replacement silt fence (300 LF)
- Land Precision Corporation — Layout stakes & as-builts (certified)
- Test Lab Inc. — 3rd-party testing
Site Logistics & Safety
- Staging area: easternmost grass area just past the pool equipment (per Addendum #1 Q6); grounds protection in place
- Russell Landscape (HOA's landscape contractor) handles any irrigation line/head repair or relocation — prior shut-down notice required
- 811 locate call placed before any excavation begins
- Pre-mobilization coordination with HOA to confirm resident & emergency access around work zones
- Daily sign-in sheets, Toolbox Talks, SWPPP inspections maintained in Documents tab (filed by week)
- Weekly progress email to HOA Board & NV5 (Fridays) summarizing the week's work and the upcoming week's closures
- Work hours: 9:00 AM → 5:00 PM weekdays (approval required for outside-hours work)
- Anticipated road closure: Mon–Wed of a single week (approx 1.5 weeks total) for removal & replacement — road plates & road-closed signs used
- Traffic cones & barriers at every work area; drive lanes partially coned where needed
- Plated crossings at driveways once steel plates are installed (Schedule IV)
- Full PPE always (hardhats, hi-vis vests, safety boots)
- Designated spotters guiding every truck movement; backup alarms on all vehicles
- End-of-day: equipment staged in designated area; worksite cleaned up; drive lanes restored
- No impact to public roadways or sidewalks maintained throughout
- If a hurricane, tropical storm, or storm surge/flooding affects the project — or requires precautionary shutdown — FFAC and the HOA will coordinate the response
- FFAC secures the work area, protects drainage paths & open excavations, and secures/relocates materials & equipment before the storm
- Operations suspended when necessary; evacuation orders & access restrictions always followed
- Written agreement on scope + pricing before any non-emergency recovery work
- Immediate protective measures may be taken for safety or to prevent further damage, with notification to HOA as soon as practicable
- Work resumes once access is authorized and site conditions have been evaluated as safe
- Kubota KX040 or equivalent excavator — demolition hammer + bucket
- Kubota U17 or equivalent excavator — bucket
- Vermeer S650TX or equivalent mini skid steer — 36" auger bit + bucket
- KCM 45ZV or equivalent loader — forks (for steel-plate handling, Schedule IV)
- Equivalent equipment may be substituted based on availability and site conditions.
Pricing & Contract Terms
- Schedule I — Earthwork, Demo & General Conditions: $72,572.17
- Schedule II — Road Construction & Site Concrete: $15,607.72
- Schedule III — Storm Drainage: $145,629.86
- Schedule IV — Rework & Temporary Access: $29,363.69
- TOTAL BID: $263,173.44
- Schedule IV includes flowable-fill demolition, jobsite cleanup / restart prep, onsite loader with forks for steel-plate handling, and steel plates for driveway trench crossings.
- Bid due date (revised per Addendum #1): Wed May 6, 2026 — 5:00 PM EDT — submitted on time
- Site inspection: Sep 22, 2026 by Arthur Wilmoth
- Insurance: COI on file (GL $1M/$2M, Umb $2M, WC statutory, Auto $1M) — through 1/1/2027
- Start: within 10 consecutive calendar days after Notice to Proceed
- Duration: 60 calendar days following Notice to Proceed
- Payment: partial release of lien from FFAC + all subs/vendors with each pay app (per NV5 Clarification)
- Pay apps routed through NV5 inspector for review before Jose Cuarta's approval
- 2-year Maintenance Bond on 110% of contract price, if required
Project Schedule — 3-Week Cleanup + 60-Day Contract
| Task | PRE-NTP · PHASE 0 CLEANUP | 60-DAY CONTRACT CLOCK (FROM NTP) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Wk 1 Cleanup | Wk 2 Cleanup | Wk 3 Cleanup | Days 1–7 | Days 8–14 | Days 15–21 | Days 22–28 | Days 29–35 | Days 36–42 | Days 43–49 | Days 50–56 | Days 57–60 | |
| PHASE 0 — SITE CLEANUP & RESTART PREP (JNL · PRE-NTP, 3 WEEKS) | ||||||||||||
| Landscape & debris cleanup | ||||||||||||
| Take down old / existing silt fencing | ||||||||||||
| Fill open trenches & holes from prior work | ||||||||||||
| Remove old pipe (prior scope) | ||||||||||||
| Flowable-fill demo + hauling (Sched IV) | ||||||||||||
| Pre-grading & restart preparation | ||||||||||||
| PHASE 1 — MOBILIZATION & SITE PREP (DAYS 1–7 FROM NTP) | ||||||||||||
| Mobilization + staging + port-o-let | ||||||||||||
| 811 locate call + utility marking | ||||||||||||
| Layout staking (Land Precision) | ||||||||||||
| NEW silt fence 300 LF (Ranger Supply) | ||||||||||||
| Inlet/M.E.S. protection (13 EA) | ||||||||||||
| PHASE 2 — EARTHWORK, PALM REMOVAL & DRAINAGE PREP | ||||||||||||
| Palm stump grinding (24 EA) | ||||||||||||
| Final pre-grading of swales (6,600 SF) | ||||||||||||
| PHASE 3 — STORM DRAINAGE INSTALLATION ($145K · CRITICAL PATH) | ||||||||||||
| Trench excavation + pipe lay (JNL) | ||||||||||||
| 196 LF 8" PVC + 162 LF 10" PVC + 96 LF 12" PVC | ||||||||||||
| Drain basins + grates (11 EA) | ||||||||||||
| Downspout assemblies + tees + reducers | ||||||||||||
| Concrete M.E.S. (2 EA, National) | ||||||||||||
| Flowable fill around pipe (CLSM 50–150 psi) | ||||||||||||
| PHASE 4 — ROAD & CONCRETE RESTORATION (MOT ACTIVE) | ||||||||||||
| Asphalt trench cut (11 SY, min 3') | ||||||||||||
| Sidewalk + curb removal + replacement (National) | ||||||||||||
| Asphalt replacement (Specialty Paving) | ||||||||||||
| Road closure Mon–Wed + road plates | ||||||||||||
| PHASE 5 — FINAL GRADING, SOD & CLOSEOUT | ||||||||||||
| Final grading of swales | ||||||||||||
| Sod placement (6,925 SF) | ||||||||||||
| SWPPP take-down + punchlist | ||||||||||||
| Certified as-builts (Land Precision) | ||||||||||||
| Final walk-through w/ Jose Cuarta · NV5 | ||||||||||||
Photo Timeline
Before, during & after documentation. Admin can upload from the Admin panel — take photos directly on-site from phone.
No photos yet
Photos will appear here as the project progresses.
Project Documents
Filed in a folder tree — Master Templates at the top (blank forms, bid packet, addendum, COI), then Week 1–9 matched to the 60-day calendar from NTP, each with Sun–Sat sub-buckets. Weekly certified payroll, sign-in sheets, safety meetings, SWPPP inspections, pay apps, and partial lien releases all live here.
The chips below filter by category across every folder in the tree.
No documents yet
Master templates (bid packet, addendum, COI, blank sign-in sheets) go in the top folder. Once construction starts, file each daily doc under Week N → day-of-week.
Project Progress
No updates yet
Progress updates will appear here once the project begins.
Field Notes
Observations, issues, RFIs, daily logs — added during construction via the Admin panel.
No field notes yet
Admin Panel
Post Progress Update
Click or drag photos here
Upload Document
Daily sign-in sheets, safety meeting notes, SWPPP inspection reports, pay apps, partial lien releases. PDFs preferred.
Click or drag file here (PDF, image, or Office doc)
Manage Documents
View or delete uploaded documents.
No documents uploaded yet.
Upload Photos
Up to 5 photos at a time. Auto-compressed for fast upload from phone.
Update Progress
Add Field Note
Manage Field Notes
No field notes yet.
Manage Updates
No updates posted yet.