Status · Awaiting Intent to Award Board meeting Tue Oct 6, 1:00 PM — Joe Santerelli, Arthur Wilmoth & John (JNL Land Management) presenting for Intent to Award with a soft Notice to Proceed for materials ordering. On approval, JNL begins the 3-week pre-mobilization site cleanup (Phase 0), then the 60-day contract clock starts at formal NTP.
Overall Project Progress
0%
Awaiting Intent to Award · Board meeting Tue Oct 6, 1pm · 3-week cleanup + 60-day contract

Stormwater & Drainage Restoration

Captiva Cay HOA · 9343 Blind Pass Rd, St. Pete Beach, FL 33706 · NV5 Project 2026-191-018 · 3-week site cleanup + 60-day contract from NTP
$263,173
Bid Total (3 Schedules + Schedule IV)
81 Days
21-Day Cleanup + 60-Day Contract
6 Phases
Phase 0 Cleanup + 5 Contract Phases
6 Subs
JNL, Specialty, National, Ranger + 2

Project Phases Click any phase to expand

P0
Site Cleanup & Restart Preparation
3 Weeks · Pre-NTP (soft-NTP window) · JNL Land Management (lead)
0%
▾
  • Week 1 — Landscape & perimeter cleanup: general debris / overgrowth removal across the project area; haul away residual material from prior work so the site is safe to re-enter.
  • Week 1–2 — Take down the old / existing silt fencing left by the prior contractor; stage for disposal.
  • Week 2 — Fill open trenches & holes left from the prior scope so the site is level and safe for Phase 1 mobilization.
  • Week 2–3 — Remove the old pipe where previously installed and no longer needed under the current drainage design.
  • Week 3 — Pre-grading & final site prep so the surveyor can lay out from a clean reference and the new work can start on Day 1 of NTP without rework.
  • JNL Land Management performs the complete reset within Schedule IV (Rework & Temporary Access) — included at $29,363.69 covering flowable-fill demo & hauling, complete jobsite cleanup & restart prep, loader w/ forks for plates, and the steel plates themselves.
Why 3 weeks: the site arrived from prior work with open excavations, abandoned silt fence, and old pipe in place — Phase 0 clears all of that so Phase 1 mobilization lands on a clean site and the 60-day contract clock isn't eaten by cleanup. JNL leads because they also carry drainage & grading subscope through Phases 2–3.
P1
Mobilization & Site Prep
Days 1 → 7 from NTP · FFAC + Land Precision + Ranger Supply
0%
▾
  • Day 1: LS Mobilization — equipment moved to the easternmost grass area past the pool equipment (per Addendum #1 Q6); MOT devices + port-o-let staged
  • Day 1–2: 811 locate call — all underground utilities marked prior to any excavation
  • Day 2–3: LS Layout staking by Land Precision Corporation
  • Day 3–5: 300 LF NEW silt fence install by Ranger Supply — both sides between unit patios and the work area (per Addendum #1 Q7)
  • Day 5–7: 13 EA Inlet / M.E.S. protection on every structure in the drainage area
  • Pre-mob coordination with the HOA for resident access + Russell Landscape for irrigation shut-down (per Addendum #1 Q1)
Phase 1 total: Mob $5,307.42 + Layout $6,462 + Silt Fence $1,650 + Inlet Prot $650 · Governs Schedule I general-conditions line items
P2
Earthwork, Palm Removal & Drainage Prep
Days 5 → 15 from NTP · JNL Land Management + FFAC
0%
▾
  • 24 EA Palm stump grinding — grind to a depth that accommodates regrading; stumps are NOT fully removed (Addendum #1 Q2)
  • 6,600 SF Pre-grading of swales — final drainage profile ahead of pipe install (built on top of the Phase 0 pre-grade)
  • Final staging of drainage materials delivered during the soft-NTP window
  • JNL continues from Phase 0 directly into pipe-work subscope through Phase 3 (no re-mob required)
Phase 2 total: Palm Grind $9,000 + Grading $18,150 · Flowable-fill demo + general cleanup moved up to Phase 0 so Phase 2 is clean earthwork + palm removal only
P3
Storm Drainage Installation · CRITICAL PATH
Days 10 → 35 · JNL (lead) + National Concrete · $145,629.86 (55% of base bid)
0%
▾
  • 196 LF 8" PVC pipe — $37,218.44
  • 162 LF 10" PVC pipe — $37,559.70
  • 96 LF 12" PVC pipe — $28,086.72
  • 11 EA 12" Drain basin w/ grate — $15,675
  • 7 EA Single downspout assemblies · 5 EA Double downspout assemblies
  • 17 EA Tees & reducers (8x6, 8x8, 10x6, sweep + 8x6 reducer)
  • 2 EA Concrete M.E.S. (National Concrete)
  • Flowable fill around pipe up to 6" limerock base per Addendum #1 Q5 — CLSM, 50–150 psi
  • Pipe bedding + bedding around basins = #57 crushed stone, except where flowable fill is required
  • Stub included in the last drainage basin for future tie-in connections
Phase 3 is the critical path — $145,629.86 · 55% of the base bid total · drives the 60-day calendar
P4
Road & Concrete Restoration
Days 25 → 50 · Specialty Paving + National Concrete + FFAC MOT
0%
▾
  • 11 SY Asphalt pavement trench cut (min 3' per spec)
  • 11 SY Asphalt pavement replacement by Specialty Paving
  • 25 LF Concrete sidewalk removal & replacement (4" thick / 3,000 psi) by National Concrete
  • 4 EA Concrete curb cuts & replacement (joint to joint — adjusted per Addendum #1 Q4)
  • MOT Plan active — anticipated road closure Mon–Wed of a single week (approx 1.5 weeks total) with road-closed signage
  • Steel plates installed over active trenches for driveway crossings (Schedule IV) + onsite loader w/ forks for plate handling
Phase 4 total: Schedule II base $15,607.72 + Schedule IV plates & loader $9,548.31 · Overlaps the back half of Phase 3
P5
Final Grading, Sod & Closeout
Days 50 → 60 · FFAC + Land Precision + NV5 Final Walk
0%
▾
  • Final grading across all disturbed areas (6,600 SF of swale)
  • 6,925 SF Sod placement — contractor's responsibility per Addendum #1 Q3 (covers all exposed soil, prevents erosion)
  • Erosion-control maintenance continues until site stabilizes
  • SWPPP take-down — silt fence & inlet protection removed after stabilization
  • LS Certified as-built plans by Land Precision Corporation
  • Final walk-through with NV5 inspector & Jose Cuarta, P.E. — punchlist resolution
  • Final pay app + partial release of lien from FFAC and every sub/vendor (per NV5 Clarification #5)
Phase 5 total: As-Builts $5,384 + Sod $25,968.75 + punchlist · Caps the 60-day program
···
Across Every Phase
Continuous requirements · MOT devices, PPE, documentation, Russell Landscape coordination
 
▾
  • FFAC provides for project duration: MOT devices, port-o-let w/ handwash station, erosion-control maintenance
  • Full PPE every day (hardhats, hi-vis vests, safety boots)
  • Designated spotters for truck movements; backup alarms on every vehicle
  • End-of-day equipment staging in designated area; worksite left clean & orderly
  • Russell Landscape coordinates irrigation shut-downs with 24h notice
  • Weekly progress email to the HOA Board + NV5 (Fridays)
  • Daily sign-in sheets, weekly Toolbox Talks, SWPPP inspections filed in Documents tab
Governing documents: Captiva Cay Bid Packet (May 6, 2026) + NV5 Addendum #1 (April 28, 2026) — both linked in Documents / Compliance folder

Team & Contacts

Project Owner
Captiva Cay HOA · NV5 Engineer of Record
  • 9343 Blind Pass Rd, St. Pete Beach, FL 33706
  • Engineer of Record — NV5, Inc.
  • Jose R. Cuarta, P.E. — Project Manager, NV5
  • 10500 University Center Drive, Suite 230, Tampa, FL 33612
  • Office (813) 765-4655
  • NV5 inspector = daily onsite contact for progress & pay-app review
Contractor
Firm Foundations Asphalt & Concrete LLC
  • Joe Santerelli — Project Manager (Primary On-Site) · 352-263-1551
  • Arthur Wilmoth — CEO / President (Secondary) · 813-853-6597
  • 10701 N Nebraska Ave, Tampa, FL 33612
  • Florida License CBC1267421 · Certified Building Contractor
  • 5 years in construction work of this type (per Bid Submittal)
  • Site inspected Sep 22, 2026 by Arthur Wilmoth
Subcontractors
6 subs on the Bid Submittal
  • JNL Land Management — Clearing, grubbing, grading, pipe work & complete site cleanup (John attending Board meeting with Joe & Arthur)
  • Specialty Paving — Asphalt pavement replacement (Schedule II)
  • National Concrete & Construction — M.E.S., sidewalk, curbing, flowable fill, catch-basin collars
  • Ranger Supply — Furnish & install replacement silt fence (300 LF)
  • Land Precision Corporation — Layout stakes & as-builts (certified)
  • Test Lab Inc. — 3rd-party testing

Site Logistics & Safety

Site Logistics & Coordination
Per MOT Plan + Addendum #1
  • Staging area: easternmost grass area just past the pool equipment (per Addendum #1 Q6); grounds protection in place
  • Russell Landscape (HOA's landscape contractor) handles any irrigation line/head repair or relocation — prior shut-down notice required
  • 811 locate call placed before any excavation begins
  • Pre-mobilization coordination with HOA to confirm resident & emergency access around work zones
  • Daily sign-in sheets, Toolbox Talks, SWPPP inspections maintained in Documents tab (filed by week)
  • Weekly progress email to HOA Board & NV5 (Fridays) summarizing the week's work and the upcoming week's closures
MOT, Road Closure & Safety
Private HOA streets · active residential community
  • Work hours: 9:00 AM → 5:00 PM weekdays (approval required for outside-hours work)
  • Anticipated road closure: Mon–Wed of a single week (approx 1.5 weeks total) for removal & replacement — road plates & road-closed signs used
  • Traffic cones & barriers at every work area; drive lanes partially coned where needed
  • Plated crossings at driveways once steel plates are installed (Schedule IV)
  • Full PPE always (hardhats, hi-vis vests, safety boots)
  • Designated spotters guiding every truck movement; backup alarms on all vehicles
  • End-of-day: equipment staged in designated area; worksite cleaned up; drive lanes restored
  • No impact to public roadways or sidewalks maintained throughout
Hurricane / Storm Protocol
Season continues through Nov 30
  • If a hurricane, tropical storm, or storm surge/flooding affects the project — or requires precautionary shutdown — FFAC and the HOA will coordinate the response
  • FFAC secures the work area, protects drainage paths & open excavations, and secures/relocates materials & equipment before the storm
  • Operations suspended when necessary; evacuation orders & access restrictions always followed
  • Written agreement on scope + pricing before any non-emergency recovery work
  • Immediate protective measures may be taken for safety or to prevent further damage, with notification to HOA as soon as practicable
  • Work resumes once access is authorized and site conditions have been evaluated as safe
Equipment Planned Onsite
Updated Sep 25, 2026 · ~90% of project duration
  • Kubota KX040 or equivalent excavator — demolition hammer + bucket
  • Kubota U17 or equivalent excavator — bucket
  • Vermeer S650TX or equivalent mini skid steer — 36" auger bit + bucket
  • KCM 45ZV or equivalent loader — forks (for steel-plate handling, Schedule IV)
  • Equivalent equipment may be substituted based on availability and site conditions.

Pricing & Contract Terms

Bid Schedule & Pricing
Submitted May 6, 2026 · 3 base schedules + Schedule IV
  • Schedule I — Earthwork, Demo & General Conditions: $72,572.17
  • Schedule II — Road Construction & Site Concrete: $15,607.72
  • Schedule III — Storm Drainage: $145,629.86
  • Schedule IV — Rework & Temporary Access: $29,363.69
  • TOTAL BID: $263,173.44
  • Schedule IV includes flowable-fill demolition, jobsite cleanup / restart prep, onsite loader with forks for steel-plate handling, and steel plates for driveway trench crossings.
Bond: Wagner Bonding and Insurance will provide Performance & Payment Bond + 2-year Maintenance Bond, if required. Bond cost reimbursed by Owner (up to 3% of amount bonded) per Bid Submittal terms.
Key Dates & Contract Terms
Per Bid Submittal + Addendum #1
  • Bid due date (revised per Addendum #1): Wed May 6, 2026 — 5:00 PM EDT — submitted on time
  • Site inspection: Sep 22, 2026 by Arthur Wilmoth
  • Insurance: COI on file (GL $1M/$2M, Umb $2M, WC statutory, Auto $1M) — through 1/1/2027
  • Start: within 10 consecutive calendar days after Notice to Proceed
  • Duration: 60 calendar days following Notice to Proceed
  • Payment: partial release of lien from FFAC + all subs/vendors with each pay app (per NV5 Clarification)
  • Pay apps routed through NV5 inspector for review before Jose Cuarta's approval
  • 2-year Maintenance Bond on 110% of contract price, if required
Full Bid Packet — 18-page PDF with Schedules of Bid Items, MOT & Hurricane plan, COI, Addendum #1, subs, and equipment list.
📄 Open PDF

Project Schedule — 3-Week Cleanup + 60-Day Contract

📅
21-day Phase 0 cleanup (soft-NTP window) → 60-day contract clock begins at formal NTP
The schedule below shows 3 pre-NTP cleanup weeks (JNL takes down old silt fencing, fills holes, removes old pipe, pre-grades) followed by the 60-day contract program sequenced by Day N from formal NTP. Target start = mid-to-late October 2026 following the Board's Intent to Award. Weather delays shift the schedule by notice. Phase 3 (drainage) is the critical path driving the back-half of the contract; Phases 2 & 4 run in parallel on the shoulders of Phase 3. » Full bid packet (PDF)
Phase 0 Cleanup
3 Weeks
JNL · pre-NTP site reset
NTP Target
~Nov TBD
After Phase 0 complete
Mobilization
Day 1
Within 10 days of NTP
Drainage Lead
Day 10–35
Phase 3 critical path
Road Closure
Mon–Wed
Phase 4 w/ road plates
Final Walk
Day 60
With Jose Cuarta · NV5
Task PRE-NTP · PHASE 0 CLEANUP 60-DAY CONTRACT CLOCK (FROM NTP)
Wk 1 Cleanup Wk 2 Cleanup Wk 3 Cleanup Days 1–7 Days 8–14 Days 15–21 Days 22–28 Days 29–35 Days 36–42 Days 43–49 Days 50–56 Days 57–60
PHASE 0 — SITE CLEANUP & RESTART PREP (JNL · PRE-NTP, 3 WEEKS)
Landscape & debris cleanup
Take down old / existing silt fencing
Fill open trenches & holes from prior work
Remove old pipe (prior scope)
Flowable-fill demo + hauling (Sched IV)
Pre-grading & restart preparation
PHASE 1 — MOBILIZATION & SITE PREP (DAYS 1–7 FROM NTP)
Mobilization + staging + port-o-let
811 locate call + utility marking
Layout staking (Land Precision)
NEW silt fence 300 LF (Ranger Supply)
Inlet/M.E.S. protection (13 EA)
PHASE 2 — EARTHWORK, PALM REMOVAL & DRAINAGE PREP
Palm stump grinding (24 EA)
Final pre-grading of swales (6,600 SF)
PHASE 3 — STORM DRAINAGE INSTALLATION ($145K · CRITICAL PATH)
Trench excavation + pipe lay (JNL)
196 LF 8" PVC + 162 LF 10" PVC + 96 LF 12" PVC
Drain basins + grates (11 EA)
Downspout assemblies + tees + reducers
Concrete M.E.S. (2 EA, National)
Flowable fill around pipe (CLSM 50–150 psi)
PHASE 4 — ROAD & CONCRETE RESTORATION (MOT ACTIVE)
Asphalt trench cut (11 SY, min 3')
Sidewalk + curb removal + replacement (National)
Asphalt replacement (Specialty Paving)
Road closure Mon–Wed + road plates
PHASE 5 — FINAL GRADING, SOD & CLOSEOUT
Final grading of swales
Sod placement (6,925 SF)
SWPPP take-down + punchlist
Certified as-builts (Land Precision)
Final walk-through w/ Jose Cuarta · NV5
Mobilization
Erosion / Silt Fence
Demolition / Palm Grind
Grading
Drainage · PVC + Basins
Concrete · MES, Flowable, Sidewalk, Curb
Asphalt Paving
Road Closure (Mon–Wed)
Cleanup / Sod
Punchlist
Inspection / Final Walk

Photo Timeline

Before, during & after documentation. Admin can upload from the Admin panel — take photos directly on-site from phone.

📷

No photos yet

Photos will appear here as the project progresses.

Project Documents

Filed in a folder tree — Master Templates at the top (blank forms, bid packet, addendum, COI), then Week 1–9 matched to the 60-day calendar from NTP, each with Sun–Sat sub-buckets. Weekly certified payroll, sign-in sheets, safety meetings, SWPPP inspections, pay apps, and partial lien releases all live here.

The chips below filter by category across every folder in the tree.

📂

No documents yet

Master templates (bid packet, addendum, COI, blank sign-in sheets) go in the top folder. Once construction starts, file each daily doc under Week N → day-of-week.

Project Progress

Overall Completion0%
Phase 0 — Site Cleanup (Pre-NTP)
0%
Phase 1 — Mob & Site Prep
0%
Phase 2 — Earthwork & Palm Removal
0%
Phase 3 — Storm Drainage Install
0%
Phase 4 — Road & Concrete Restoration
0%
Phase 5 — Final Grading, Sod & Closeout
0%
🚧

No updates yet

Progress updates will appear here once the project begins.

Field Notes

Observations, issues, RFIs, daily logs — added during construction via the Admin panel.

📝

No field notes yet

Admin Panel

⚙ Post Progress Update

📷

Click or drag photos here

📂 Upload Document

Daily sign-in sheets, safety meeting notes, SWPPP inspection reports, pay apps, partial lien releases. PDFs preferred.

📂

Click or drag file here (PDF, image, or Office doc)

🗂 Manage Documents

View or delete uploaded documents.

No documents uploaded yet.

📷 Upload Photos

Up to 5 photos at a time. Auto-compressed for fast upload from phone.

📈 Update Progress

📝 Add Field Note

📝 Manage Field Notes

No field notes yet.

🗒 Manage Updates

No updates posted yet.

Admin Access

← Back to Dashboard